Park Avenue and Deer Valley Drive Are Finished. The Bus They Were Built For Arrives in 2028.

The orange cones are coming off State Route 224 for the winter. In early October, High Valley Transit said its first full construction season on the Bobsled Express, the bus rapid transit line between Kimball Junction and Old Town, was nearing its end. Main construction stops until spring 2027. Deer Valley is targeting Saturday, December 5, 2026 for opening day, so the corridor will clear just before ski traffic returns.

For Lower Deer Valley, the result is lopsided. The Park Avenue and Deer Valley Drive intersection is the one segment High Valley Transit lists as complete. But the free, frequent bus that justified the work won't carry passengers until 2028. The change you'll actually notice on a bus this season comes from Park City Transit's schedule, not from new pavement.

What got finished at the bottom of Deer Valley Drive

High Valley Transit calls this stretch Segment 1. Its 2026 recap says "major work is complete" there. The finished list:

  • New turn lanes to improve traffic flow
  • New traffic signals and street lighting
  • New sidewalks
  • Drainage improvements
  • Rebuilt curbs, gutters, driveways and paved surfaces that construction had torn up

KPCW's October 6 report included an aerial photo of the intersection with its added left and right turn lanes. The station said the project overall is running ahead of schedule. Getting there took real disruption. In mid-June, Park Avenue at Deer Valley Drive closed overnight for storm-drain work, with a detour along 15th Street, Empire Avenue and Deer Valley Drive.

This winter is the first ski season the new intersection will handle resort traffic. It's also a finished piece sitting at the far end of a line that's mostly still under construction.

North of the intersection, SR-224 stays mid-construction until 2028

Drive from Deer Valley Drive toward Kimball Junction and you pass every stage of this project. High Valley Transit's progress page and its 2027 plan show the corridor this way, roughly from south to north:

Stretch of SR-224 Status after the 2026 season What's next
Park Ave. & Deer Valley Dr. Major work complete Nothing major listed
McPolin Barn to Holiday Ranch Loop Rd. Ahead of schedule; landscaped medians, paving, striping and drainage done Northbound widening from McPolin Barn to Kearns Blvd. in 2027
Kearns Blvd. to White Pine Canyon Drainage work started early More intensive construction in 2027
Bear Hollow Dr. to White Pine Canyon Rd. Southbound side still to come Southbound widening starts first in spring 2027
Olympic Blvd. to Canyons Resort Dr. Major drainage, utility relocation, retaining wall rebuilt, new detention pond, signals improved at Old Ranch, Silver Springs Dr. and Olympic Blvd. Bobsled and Cutter Lane stations, already started, continue

The northern end is where the new lanes will get used first. Gabe Shields, High Valley Transit's chief development officer, told KPCW that some sections will have dedicated bus lanes once the cones come out:

"Where we've completed work between Olympic [Parkway] and Canyons [Drive], we're essentially going to have the BRT running just about fully complete."

That stretch sits near Kimball Junction and Canyons Village, at the opposite end from Lower Deer Valley. For this winter, the most complete transit lanes are a seven-mile route away from the most complete intersection. High Valley Transit says winter work will be limited to local bus stops as weather allows. Traffic control comes down and the trails that were closed reopen. In 2027, the station work moves to canopies, real-time information boards, lighting and landscaping.

The Bob's opening date has moved twice

When it's finished, the Bobsled Express, which High Valley Transit calls the Bob, will run about seven miles between Kimball Junction Transit Center and Old Town Transit Center, with a stop at Canyons Village Transit Center. The agency's FAQ names four new stations: Bobsled, Cutter, Thaynes and Snow Creek. The three transit-center stops also get upgrades. The dedicated lanes will be open to High Valley Transit, Park City Transit and school buses.

The planned service:

  • Buses every 10 to 15 minutes, seven days a week
  • Running from 6 a.m. to midnight, according to the Park Record's March report
  • Free, like every High Valley Transit service

Here's how the timeline has shifted. In January 2024, KPCW reported that the project had first been expected to open in late 2025, and quoted the agency's director as hoping for full operation by 2027. Construction finally began on April 6, 2026. The current target is fall 2028 in KPCW's October story and "the end of 2028" in High Valley Transit's FAQ. No source gives an exact launch day.

Counting from today, the 2026-27 and 2027-28 ski seasons both pass before the Bob is scheduled to carry riders. The intersection at the bottom of Deer Valley Drive is getting two winters of use before the bus it was rebuilt for arrives.

This winter's transit change is a new schedule

Park City Transit, the city-run system, is making the one bus change riders will see before 2028. On October 1, 2026, city transportation staff presented the 2026-2027 Winter Service Plan to City Council. Its stated aim is to "address recurring issues with bus reliability."

The plan changes how the timetable gets built:

  1. Scheduled runtimes come from how long each segment of a route actually took last winter at different times of day. The same runtime no longer applies all day long.
  2. Frequency follows how long a bus takes to finish its full loop, instead of a round number like every 30 minutes at key stops. Staff say this lets them add service on some routes and cut unneeded layovers.
  3. Most buses stay on one route. That way a delay on one line doesn't carry over into the rest of the network.
  4. More recovery time gets built in during peak congestion.

TownLift's coverage of the work session spelled out the trade-off. Some routes could have slightly longer scheduled trip times during peak congestion, while other times of day could see shorter runtimes and more frequent buses. Schedules will still be published, and buses won't run on a constantly changing timetable. Council backed the new scheduling approach. It put the proposed 10-Pink route into Quinns Junction on hold until staff bring back more information on demand.

Taken together, Lower Deer Valley gets a better-built intersection and a timetable that admits winter traffic slows the buses down.

What hasn't been published for Snow Park yet

Some of the details that matter most at the Snow Park end of Deer Valley Drive are still unannounced as of mid-October.

Park City Transit's winter service usually starts in early December and runs through mid-April. The city's routes page still links the 2026 summer timetable. For comparison, last season's winter schedule started December 8, 2025. It added frequency on the Red, Blue and Green routes and brought back express service from Richardson Flat to Park City Mountain and Deer Valley. The October staff report mentions express routes 7 and 8 serving the resort bases from Richardson Flat. It doesn't publish this winter's route map or frequencies for the Deer Valley corridor.

Deer Valley's own parking guide was last updated October 31, 2025. It describes free express buses every 15 minutes from Richardson Flat to Snow Park, but only for December 7, 2025 through March 31, 2026. The same guide lists Snow Park parking as free, with premium paid parking at Jordanelle. That was last season's setup. The resort hasn't confirmed it for 2026-27 in anything published so far.

The redevelopment of the Snow Park base has no date attached. In April, Deer Valley told the Park Record it had no Snow Park construction planned for summer 2026 and no updated project timeline. The approved plans still include a garage of up to 1,971 spaces and an underground transit center. Until a timeline appears, the rebuilt intersection at the bottom of Deer Valley Drive is the only finished piece of new transportation infrastructure on the drive up to the resort.

If you're weighing a Lower Deer Valley home, its bus access, or the Snow Park redevelopment against what the corridor will look like in 2028, Wayne Levinson can walk you through how these timelines may affect a specific address. Schedule a personalized Park City property consultation.